European Medicines Agency To Be Hit Hard By Brexit Move, It Says

The European Medicines Agency (EMA), which is oversees the scientific evaluation, supervision and safety of medicines in the European Union, will scale back activities through 2019 due to significant staff loss when it moves from London to Amsterdam in March 2019 as a result of Brexit. Some of the areas that could be affected include the agency’s work at the international level on supply chain integrity, antimicrobial resistance, vaccines, and clinical data analysis.

The EMA has determined that it will lose some 30 percent of staff in the move precipitated by the United Kingdom’s exit from the EU, it said in a 1 August release detailing its plans.

Staff losses include those who will not move to Amsterdam and the loss of 135 short-term contract posts due to Dutch employment rules, EMA said.

The move is being managed in phases, with the next phase starting by October and involving scaling back or suspending some activities. EMA refers to its international collaboration, which will be dramatically affected, as a “central pillar in its strategy to protect public health” and says that some 80 percent of active substances used in Europe come from outside the EU.

The full EMA announcement is reprinted below:

Brexit preparedness: EMA to further temporarily scale back and suspend activities

Next phase of business continuity plan aimed at securing essential public and animal health activities

The European Medicines Agency (EMA) will launch the next phase of its business continuity plan on 1 October 2018 at the latest. This will allow the Agency to safeguard core activities related to the evaluation and supervision of medicines, while it has to intensify its preparations for the physical move to Amsterdam in March 2019 and cope with significant staff loss.

The temporary cuts in activities are required because it has also become clear that the Agency will lose more staff than initially anticipated. Staff who will not relocate to Amsterdam have already started to leave the Agency and this trend is expected to accelerate. In addition, due to the employment rules in the Netherlands, 135 short-term contract staff will no longer be able to work for EMA. Overall, EMA expects a staff loss of about 30%, with a high degree of uncertainty regarding mid-term staff retention.

EMA has put in place supporting measures to facilitate the relocation of staff to Amsterdam and additional support is provided by the Dutch government. Other mitigating actions, such as a comprehensive staff recruitment programme, are already underway. However, in the short- to mid-term EMA will have to reprioritise its resources to fully maintain its core activities related to the evaluation and supervision of medicines to the level of quality and within the timelines expected.

Following the implementation of phase 1 and 2 of the business continuity plan, in phase 3 EMA will start to temporarily scale back or suspend additional activities through to 2019. This contributes to protecting EMA’s essential public health activities and allows for training of EMA staff who will be re-assigned to new duties ahead of the peak relocation time which will start in early 2019.

Activities initially impacted by phase 3 include:

  • Collaboration at international level, which will be temporarily scaled back to focus primarily on product-related requests, supply-chain integrity and procedures under Article 58; in other areas, such as the harmonisation of global medicine regulation, EMA will only take a reactive role; EMA’s engagement in other global public health issues such as antimicrobial resistance or vaccines will be maintained as long as possible, but reviewed on a case-by-case basis;
  • Development and revision of guidelines, which will be temporarily limited to those guidelines that address an urgent public/animal health need or are necessary to support and facilitate preparations for Brexit;
  • Holding of non-product-related working parties, which will be temporarily reduced as a consequence of the scaling back of guideline development or revision;
  • Programmes and projects, where activities in relation to project governance will be reduced in line with the reduction/suspension of projects;
  • Organisation and attendance at stakeholder meetings, which will be limited to Brexit-related interactions;
  • Clinical data publication, for which the launch of new procedures will be temporarily suspended as of 1 August 2018; data packages submitted for medicines until the end of July 2018 will be processed and finalised.

The implementation date for phase 3 of EMA’s business continuity plan is 1 October at the latest. Detailed plans for the implementation of these measures are currently being developed and will be communicated to stakeholders concerned and the public as soon as they are available.

 

Combat the infodemic in health information and support health policy reporting from the global South. Our growing network of journalists in Africa, Asia, Geneva and New York connect the dots between regional realities and the big global debates, with evidence-based, open access news and analysis. To make a personal or organisational contribution click here on PayPal.